  • Approved a $394,485 change order for the Riverside Ice Arena roof project (4-1 vote, Rangel opposed)
  • Purchased a new GEHL AL 650 wheel loader for $85,173 to support park maintenance operations
  • Adopted several new policies including Fund Balance Policy, Investment Policy, and policies on AI use in hiring, theft control, and preventative maintenance
  • Received favorable results from PDRMA Risk Management Review with above-average scores

Decisions & votes

Approved unanimously:

  • Meeting agenda and December 9, 2025 minutes (Noble abstained on minutes)
  • Expense approval report (12/4/2025–1/8/2026)
  • Purchase of 2026 GEHL AL 650 wheel loader from Casey Equipment for up to $85,173
  • Fiscal Year 2025 audit engagement letter with Lucas Group not to exceed $20,000
  • Fund Balance Policy
  • Resolution No. 01-13-26 adopting the Investment Policy
  • AI Use in Hiring Policy, Theft Control Guidelines, and Preventative Maintenance policies
  • Official statement on Solar Farm Lease Requests

Approved 4-1:

  • Change order for DPI Construction for Riverside Ice Arena roof project for $394,485 (Rangel voted no)

Discussion items

  • Childcare Assistance Program Funding discussed during Executive Director report
  • Ice Hogs Night review and Special Recreation 5K scheduled for end of February mentioned in recreation report
  • Land composition issues discussed related to the ice arena roof project
  • Background and need for wheel loader purchase reviewed
  • Purpose of Investment Policy and AI use in hiring practices discussed
  • GASB rules mentioned in context of Fund Balance Policy and solar farm statement

Financial / operational notes

  • PDRMA Risk Management Review Results showed very favorable outcomes with above-average scores for the Park District
  • Executive Director annual review timeline established; board members to submit evaluations to Noble including review of 2025 goals, with 2026 goals to be completed in February
  • Major capital expenditures: $394,485 for ice arena roof change order and $85,173 for wheel loader
  • FY2025 audit budgeted at up to $20,000